The negligence of public administration delays the investments

The extended administration procedures and failure in meeting the deadlines of issuing the construction and use permit delay the investments planned by the developers. As follows from the inquiry conducted by the Polish Association of Developers 47% of construction permits and 95% of decisions on building conditions, in last three years was issued after the statutory time limit of two months. Echo Investment claims, that because of the negligence of public administrations, the company has realized only 7 from 20 planned investments.