The Upper One complex has made significant progress in its construction, with the office section already reaching the 14th floor. The building has reached 41% of its planned final height. Work is progressing at a rate of approximately one floor per week. The office section will provide a total of 35,900 sqm.
According to the approved work schedule, the installation of the building's facade system will begin this quarter. It should be noted that the Upper One architectural design has received the “Best Market Practice” certificate, confirming the high standards of the investment.
The work should be completed in Q1 2027.